Completed projects for the year 2015

رجوع

Investment plan projects

project name

Construction of Computer Engineering Building

The total area of the project

  8500  m2

Area of land on which the project is built

  1214  m2

Total cost of the project

9,500,000.000 ID

The executing agency of the project

al-mamar  company for genral contacting 

Start date of work

11/12/2011

Date of completion

15/  6/2015